Project

Liberty Hospital Non-Oncology Infusion Clinic

  • Market Healthcare
  • Location Liberty, Missouri
  • Delivery method Bid-Build

Outpatient Infusion Clinic Renovation

A complete demolition and renovation that transformed two administrative spaces at Liberty Hospital into a new outpatient clinic for non-oncology infusions. Located near the hospital’s main entrance, the project required extensive coordination to modify underfloor plumbing above the cafeteria serving area and adapt the existing MEPF infrastructure. The clinic was completed in three months without disrupting adjacent hospital services.

Complete demolition and renovation of two administrative spaces
New outpatient clinic for non-oncology infusions
Underfloor plumbing modifications above the cafeteria serving area
Existing MEPF infrastructure modified for the new clinical space
Connections to existing HVAC mains and electrical panels
Coordination with hospital departments, facilities, and infection prevention teams
Completed in three months without disrupting adjacent hospital services

Project

Liberty Hospital Urology Clinic Renovation

  • Market Healthcare
  • Location Liberty, Missouri
  • Delivery method Bid-Build
  • Architect Pulse Design Group

Urology Clinic Modernization

A single-phase renovation of an existing urology clinic at Liberty Hospital designed to modernize the space and prepare it for new staff. Completed in three months, the project included cosmetic and MEP upgrades that created an updated clinical environment to support continued patient care.

Single-phase renovation completed in three months
Cosmetic upgrades throughout the existing clinic
MEP upgrades supporting the renovated space
Modernized clinical environment designed to accommodate new staff
Design by Pulse Design Group

Project

Freeman Hospital West Cath Lab #3 Remodel

  • Market Healthcare
  • Location Joplin, Missouri
  • Architect HMN Architects
  • Owner Freeman Health System

A complete renovation of Cath Lab #3 at Freeman Hospital West designed to support a new state-of-the-art, ceiling-mounted C-arm X-ray system. The project included interior demolition and MEP system modifications, along with detailed coordination with Philips to meet the equipment’s technical requirements. Through careful planning and a robust infection-control program, the work was completed next to three operating cath labs without disrupting standard or emergency procedures.

Complete interior demolition and renovation

New ceiling-mounted C-arm X-ray system

Mechanical, electrical, and plumbing system modifications

Detailed coordination with Philips

State-of-the-art medical technology

Construction adjacent to three operating cath labs

Hospital operations maintained throughout construction

Comprehensive infection-control program

Project

Naval Medical Center San Diego DDC System Restoration

  • Market Critical Infrastructure, Federal, Healthcare
  • Location San Diego, California
  • Delivery method Design-Build
  • Architect United Excel Design

A design-build modernization of the Direct Digital Control system within Building 1 at Navy Medical Center San Diego, a five-story, 953,306-square-foot healthcare facility. The project replaces outdated and unsupported controls with a modern, reliable, and maintainable system that supports HVAC performance and helps maintain a healthy, code-compliant hospital environment.

Approximately 1,500 variable air volume units

New sequences of operation for new and existing DDC controllers

Modernized controls for cooling, heating, humidification, and ventilation

Work performed within an active medical facility

Careful coordination to minimize disruptions to patient care and hospital operations

Comprehensive infection control and prevention measures

Improved system reliability and long-term maintainability

Project

F.E. Warren Air Force Base Facilities Modernization

  • Market Federal, Healthcare
  • Location Cheyenne, Wyoming
  • Delivery method Design-Build

Medical Facilities Modernization

A comprehensive modernization of Building 160 and the Veterinary Clinic at F.E. Warren Air Force Base designed to improve patient care, staff efficiency, and mission readiness. The project modernized multiple clinical departments, created a new medical mall, upgraded major building systems, and improved circulation and wayfinding. Detailed phasing and two temporary facilities allowed essential medical services to remain operational throughout construction.

Modernization of the Building 160 medical clinic
New medical mall and main entrance
Renovations to Pharmacy, Laboratory, Radiology, Optometry, Dental, Pediatrics, Women’s Health, Public Health, and additional departments
New ground-up Veterinary Clinic
Ambulance garage addition
Two temporary phasing facilities with covered connections to the main clinic
Upgraded mechanical, electrical, plumbing, fire protection, communication, and life safety systems
Improved patient circulation, departmental adjacencies, and wayfinding
Infection control barriers and negative-air measures
Phased construction within an operational medical facility

Project

Minot Air Force Base Medical Clinic Modernization

  • Market Federal, Healthcare
  • Location Minot Air Force Base, North Dakota
  • Delivery method Design-Build

Comprehensive Military Medical Clinic Modernization

A complex, multi-phased modernization of a 331,981-square-foot military medical clinic designed to improve patient care, operational efficiency, and long-term facility performance. Completed while the clinic remained fully operational, the project transformed outdated departments into modern healthcare environments with improved layouts, upgraded building systems, and stronger connections between related services.

Approximately 14 phases completed within a fully operational medical clinic
Renovations to Dental, Behavioral Health, Physical Therapy, Radiology, Laboratory, Optometry, Ambulance Services, and additional departments
Two temporary phasing facilities and multiple swing spaces
New three-story glass and steel monumental staircase
Upgraded HVAC, electrical, and life safety systems
Replaced main entrance and exterior canopy
Improved departmental layouts and functional adjacencies
LEED Silver certification goals
Lean and evidence-based design principles
Infection control measures recognized by the Air Force Medical Support Agency as a “Best Practice for Construction/Renovation”

Project

Edwards Air Force Base Medical Facilities Modernization

  • Market Federal, Healthcare
  • Location Edwards Air Force Base, California
  • Delivery method Design-Build

Supporting Military Healthcare Through Facility Modernization

A comprehensive modernization of multiple medical facilities supporting the 412th Medical Group at Edwards Air Force Base. The project delivered updated clinical, laboratory, administrative, and support spaces designed to improve operational efficiency and meet evolving mission requirements. The work included renovations, facility expansions, new construction, and temporary phasing facilities that allowed essential healthcare services to continue throughout construction.

Modernization of dental, laboratory, education, physical therapy, and administrative spaces
New ground-up physical therapy facility
Expanded temperature-controlled ambulance garage
Three temporary phasing facilities totaling approximately 15,000 square feet
Specialized HVAC systems supporting required temperature, humidity, air pressure, and air-change levels
Upgraded architectural, mechanical, electrical, plumbing, fire protection, and communication systems
Advanced access control, intrusion detection, and security systems
Durable, cleanable finishes designed for clinical and laboratory environments
Site improvements including utilities, landscaping, parking, grading, and drainage
Commissioning and interoperability testing of major building systems

Project

Liberty Hospital TreeHouse Renovation

  • Market Healthcare
  • Location Liberty, Missouri
  • Delivery method Design-Bid-Build

A Home Away From Home, Designed for Comfort

A thoughtful renovation designed to provide comfort, support, and a welcoming place to stay for the families of Liberty Hospital patients. Completed in Fall 2024, the modernized TreeHouse features accessible guest accommodations, private sleeping rooms and baths, gathering spaces, and upgraded building systems that will serve guests and the surrounding community for years to come.

Private guest rooms and bathrooms
Accessible bathroom and shower upgrades
Renovated hearth room kitchen
Quiet room and community gathering areas
Finished lower-level spaces for guest and community use
Expanded reception and entry area
New accessible vestibules and automated doors
Updated manager’s apartment kitchen and loft bathroom
Replaced exterior cedar decks and railings
New HVAC equipment and control systems
Energy-efficient LED lighting upgrades
Refreshed finishes throughout the facility

Project

Olathe Health Rehabilitation Clinic

  • Market Healthcare
  • Location Olathe, Kansas
  • Delivery method Design-Bid-Build

Designed for Recovery, Built Around Patient Care

A nearly 10,000-square-foot renovation that transformed the second floor of the Olathe Health Rehabilitation Clinic into a modern physical therapy environment designed to support patient recovery, staff efficiency, and exceptional care. Completed within an active healthcare facility, the project required careful coordination and infection control measures to minimize disruptions throughout construction.

Approximately 9,782 square feet of renovated space
Modernized physical therapy and rehabilitation areas
Interior demolition and space reconfiguration
HVAC system modifications
Updated lighting systems
Infection control measures
Construction completed within an operational healthcare facility

Project

Peterson Space Force Base Medical Clinic Renovation

  • Market Federal, Healthcare
  • Location Colorado Springs, Colorado
  • Delivery method Design-Build

Built for Better Care and Mission Readiness

A phased renovation and expansion designed to enhance patient care while keeping essential medical services operational throughout construction. The project modernized key departments, including Pharmacy, Pediatrics, Women’s Health, Family Health, and Public Health, while adding a new mechanical room and front entrance. Architectural, MEP, life safety, and functional upgrades created an efficient, welcoming facility for service members and their families.

New mechanical room addition
New front entrance addition
Mechanical yard ATFP upgrades
Renovated main waiting area and front entrance
Terrazzo flooring and specialty finishes
Custom mountain feature wall
Curved acoustical ceiling clouds
Temporary facility for department relocations during construction